The building can accommodate up to 296 clients in four 50-man dorms, three 24-man dorms, and one 24-woman dorm. The steel clear span design allows for a large open seating and activity area, in addition to two large partitionable classrooms, a full commercial kitchen, multiple administrative offices and counselor rooms, a control room, and a nurses area. Ramtech was responsible for the full site development of the four acres that accommodate the building, 40 parking spaces, two basketball courts, and two covered pavilions.
Project Size: 31,752 sq ft
Construction: IBC Type V-b
Contract Type: Design-Build
Facility Use: Residential reintegration facility
Description: Dallas Transitional Center
Completion: 250 days including design
]]>Project Size: 432,000 sq ft – (24) 2-story buildings 48,000 sq ft (6) 1-story buildings
Completion: BCT-1 & 2 March 2009 BCT-3 March 2010
Construction Type: Type III
Facility Use: Company Operation Facilities
Description: Multi-story & single-story buildings Designed exteriors to match existing base facilities Masonry wainscot with stucco-clad metal panel
]]>
The Type V-B meets all the latest model building codes and the areas structural criteria for Seismic Category A, a 170 mile-per-hour Exposure D wind load, and a .54 psi Blast Overpressure Rating. The building features individual private offices that use a glass interior storefront partition system around the perimeter of the interior and a large L-shaped clear span office area for multiple cubicles. There are also two large training and conference rooms, and a separate crew room and locker storage area. To accommodate the Gulf Coast areas high humidity, Lennox roof-mounted HVAC units were utilized.
Project Size: 16,800 sq ft
Construction: Type V-b
Contract Type: Negotiated
Facility Use: Engineering and office space
Description: Clear span office area for multiple cubicles, crew room, two conference rooms, and locker storage
Completion: 165 days
]]>